| March 2012 |
Interior work progresses, rental lease-up starts |
| February 2012 |
Interior work progresses |
| January 2012 |
Interior work progresses |
| December 2011 |
Weatherization completed, brick work continues, interior work started |
| November 2011 |
Exterior, paving, roofing completed, exterior brick work continues |
| October 2011 |
Framing, roofing continues, window frames installed, |
| September 2011 |
Framing continues upward |
| August 2011 |
Basement and first floor framing underway |
| July 2011 |
Foundations finished, lower walls and steel beams started |
| June 2011 |
Site prep and foundation construction |
| May 2011 |
Site excavation and clean-up continues |
| April 2011 |
Site excavation and clean-up |
| March 2011 |
Existing building demolition and clean-up |
| Nov.2010 - February 2011 |
Site preparation, scrap and asbestos removal for demolition |
| October 2010 |
Financing Completed and Closed, Groundbreaking Celebrated |
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|
| |
|